Rea Vaya phase 1C Sandton loop weekly report
    Press Release|April 7, 2017

    Rea Vaya phase 1C Sandton loop weekly report

    Phase 2: West Street South bound [between Maude Street and Rivonia Road]: 95% complete

    Rea Vaya phase 1C Sandton loop weekly report
    Phase 2: West Street South bound [between Maude Street and Rivonia Road]: 95% complete - Storm water pipes: Excavation: 100% complete - Laying of pipes: 100% complete - Backfill: 100% complete - New Kerb inlets: 100% complete -New storm water manholes: 100% complete - Installation of sleeves & manholes: 100% complete - Road Widening: 100% complete - Pedestrian side walk: 100% complete – Section outside Old Mutual to be excluded - Base repairs: 100% complete - Asphalt overlay: 100% complete - Ramp outside Gautrain station: 100% complete - Extra work Gautrain station: 0% (moving of steel hand railings, new hand railings on steps, wheel chair access ramp) - Road signage for back-to-back kerbs of cycle lanes: 0% complete - Bull nose for back-to-back kerbs of cycle lanes: 100% complete - Bell mouths: 0% complete - Road marking: 100% complete - Planting of trees: 100% complete [West Street North bound outside Gautrain station] - Street lights: 100% complete - Egoli gas pipeline: 0% complete Phase 2: West Street North bound outside Garden Court [between Maude Street and Alice lane]: 85% complete - Expose existing services: 100% complete - Excavation to sidewalk level: 100% complete -Roadbed preparation: 100% - Layer works to extend pedestrian side walk: 100% complete - New paving to extend sidewalk to retaining wall: 100% complete - New retaining wall: 100% complete - New benches: 100% complete - Hedge: 100% complete - Bell mouths: 0% complete -Re-location of palisade fence: 100% complete Phase 2: Re-alignment of West Street North bound [between Fredman Drive and Grayston Drive]: 90% complete - New kerbline of median: 100% complete - Roadbed for median: 100% complete - Layerworks for median: 100% complete - Paving of median: 100% complete - Asphalt for median: 100% complete - Removal of median street lights: 100% complete - Landscaping of median: 80% complete - Bell mouths: 0% complete - New kerbline for pedestrian sidewalk on West Street South bound: 100% complete - Roadbed for pedestrian sidewalk on West Street South bound: 100% complete - Layerworks for pedestrian sidewalk on West Street South bound: 100% complete - Paving of pedestrian sidewalk on West Street South bound: 100% complete Phase 2: Rivonia Road [between West Street and Fredman Drive]: 98% complete East bound (Section outside Old Mutual to be excluded) and 97% complete West bound (Section outside Gautrain Hotel to be excluded) - Storm water pipes: Excavation: 100% complete (East bound and West bound) - Storm water pipes: Laying of pipes: 100% complete (East bound and West bound) - Stormwater pipes: Backfill: 100% complete (East bound and West bound) - Paving of medians: 100% complete - Installation of sleeves and manholes: 100% complete East bound (excluding section outside Old Village walk) and 100% complete West bound (excluding section outside Gautrain Hotel) - New pedestrian sidewalk: 100% complete East bound (excluding section outside Old Village walk) and 100% complete West bound (excluding section outside Old Village walk) - BRT lane strengthening: 100% complete (excluding section outside Old Village walk) - Base repairs: 100% complete - New asphalt overlay: 100% complete - Road marking: 30% complete - Bell mouths: 0% complete - Street lights: 100% complete Phase 2: Maude Street [between West Street and Rivonia Road]: 99% complete East bound and 98% complete West bound - Storm water pipes: Excavation: 100% complete (East bound and West bound) - Laying of pipes: 100% complete (East bound and West bound) - Backfill: 100% complete (East bound and West bound) - Installation of sleeves: 100% complete: Leonardo excluded (East bound and West bound) - Expose existing services: 100% complete (East bound and West bound) - Roadbed preparation: 100% complete Leonardo excluded (East bound) and (West bound) - Layerworks: 100% complete Leonardo excluded (East bound) and (West bound) - New paving Pedestrian side walk: 100% complete: Leonardo excluded (East bound) and 100% (West bound) - New paving cycle lane: 100% complete: (West bound) and 100% complete East bound Leonardo excluded - New paving vehicular lanes: 100% complete: (West bound) and 100% complete East bound Leonardo excluded - Bell mouths: 0% complete - Rumble blocks for cycle lanes: 100% complete (excluding Old Village walk) - Painting of cycle lanes: 100% complete - New dust bins: 100% complete - Road marking: 100% complete (East bound and West bound) - Road signage for metered taxis: 100% complete - Egoli gas: 0% complete Phase 2: Maude Street [between West Street and 5th Street]: 45% complete - Setting out: 100% complete - Exposing existing services: 50% complete - Relocation of existing services: 50% complete - New Storm water pipes: 50% complete - New Kerb inlets: 20% complete - New Sleeves: 50% complete - Layerworks for new pedestrian side walk: 50% complete - New Pedestrian side walk: 30% complete - Layerworks for road: 50% complete - Paving of median: 0% complete - Bell mouths: 0% complete - Removal of median street lights: 100% complete - New median street lights: 0% complete - Re-alignment of median: 0% complete - New paving of road: 0% complete Phase 2: Fredman Drive [between Rivonia Road and 5th Street]: 99% complete (West bound) & 99% complete (East bound) - Storm water pipes: Excavation: 100% complete (East bound and West bound) - Laying of pipes: 100% complete (East bound and West bound) - Backfill: 100% complete (East bound and West bound) - New Kerb inlets: 100% complete (West bound) and 100% (East bound) - Installation of sleeves: 100% complete (West bound and East bound) - Expose existing services: 100% complete (West bound and East bound) - Lane widening by narrowing of median: 100% - Paving of median: 100% - New sleeves in median: 100% - Base repairs: 100% complete (West bound) - Base repairs: 100% complete (East bound) - Crack sealing: 100% complete (East bound) - BRT lane strengthening: 100% complete (West bound) - Asphalt overlay: 100% complete (West bound) and 100% complete (East bound) - Bell mouths: 0% complete - New Pedestrian side walk: 100% complete (West bound) and 100% (East bound) - Road marking: 70% complete - New BRT station: 100% complete - Street lights: 100% complete Phase 2: 5th Street [between Fredman Drive and Rivonia Road]: 70% complete (East bound) section outside Da Vinci excluded and 95% complete (West bound) section outside WBHO excluded - Installation of sleeves: 70% complete (East bound) and 100% complete (West bound) - New Pedestrian side walk: 70% complete (East bound) and 100% complete (West bound) - Retro-fitting of median: 100% - Landscaping of median: 100% complete - Raised driveways: 100% complete (West bound) - Base repairs: 100% complete - Asphalt overlay: 100% (East bound) - Road marking: 0% (East bound) - Bell mouths: 0% complete - Street lights: 100% complete Trunk route: Katherine Street [between West Street and 5th Street]: 100% complete - BRT lane strengthening: 100% complete - Paving of side walk East bound: 100% complete - New kerb line median: 100% complete - Paving of median: 100% complete - Base repairs: 100% complete - AP-1 Asphalt paving: 100% - Road marking: 100% complete - Street lighting: 100% complete - Sleeves for street lighting: 100% complete Trunk route: 5th Street [between Rivonia Road and Katherine Street]: 100% complete - BRT lane strengthening: 100% complete - Road widening: 100% complete - Lowering existing services: 100% complete - Paving of median: 100% complete - Base repairs to South bound carriageway: 100% complete - AP-1 Asphalt paving: 100% - Road marking: 100% complete - Street lighting: 100% complete - Sleeves for street lighting: 100% complete Trunk route: West Street [between Rivonia Road and Katherine Street]: 100% complete - BRT lane strengthening: 100% complete - AP-1 Asphalt paving: 100% - Sleeve crossing: 100% complete - Manhole for sleeves: 100% complete - Reinstating Kerb inlet: 100% - Base repairs: 100% complete - Road marking: 100% complete - Street Lighting: 100% complete - Sleeves for street lighting: 100% complete Issues during the week: - None Report prepared by: Isaac Ojungu Pr.Eng Msc Eng (Transport) Resident Engineer BERGSTAN SA