Rea Vaya phase 1C Sandton loop weekly report
20 March 2017

Phase 2: West Street South bound [between Maude Street and Rivonia Road]: 95% complete


- Storm water pipes: Excavation: 100% complete
- Laying of pipes: 100% complete
- Backfill: 100% complete
- New Kerb inlets: 100% complete
- New storm water manholes: 100% complete
- Installation of sleeves & manholes: 100% complete
- Road Widening: 100% complete
- Pedestrian side walk: 100% complete – Section outside Old Mutual to be excluded
- Base repairs: 100% complete
- Asphalt overlay: 100% complete
- Ramp outside Gautrain station: 100% complete
- Extra work Gautrain station: 0% (moving of steel hand railings, new hand railings on steps, wheel chair access ramp)
- Road signage for back-to-back kerbs of cycle lanes: 0% complete
- Bull nose for back-to-back kerbs of cycle lanes: 40% complete
- Road marking: 100% complete
- Planting of trees: 100% complete [West Street North bound outside Gautrain station]
- Street lights: 100% complete
- Egoli gas pipeline: 0% complete


 


Phase 2: West Street North bound outside Garden Court [between Maude Street and Alice lane]: 85% complete


- Expose existing services: 100% complete
- Excavation to sidewalk level: 100% complete
- Roadbed preparation: 100%
- Layer works to extend pedestrian side walk: 100% complete
- New paving to extend sidewalk to retaining wall: 100% complete
- New retaining wall: 100% complete
- New benches: 100% complete
- Hedge: 0% complete
- Re-location of palisade fence: 100% complete


 


Phase 2: Re-alignment of West Street North bound


[between Fredman Drive and Grayston Drive]: 90% complete


- New kerbline of median: 100% complete


- Roadbed for median: 100% complete
- Layerworks for median: 100% complete
- Paving of median: 100% complete
- Asphalt for median: 100% complete
- Removal of median street lights: 100% complete
- Landscaping of median: 60% complete
- New kerbline for pedestrian sidewalk on West Street South bound: 100% complete
- Roadbed for pedestrian sidewalk on West Street South bound: 100% complete
- Layerworks for pedestrian sidewalk on West Street South bound: 100% complete
- Paving of pedestrian sidewalk on West Street South bound: 100% complete


Phase 2: Rivonia Road [between West Street and Fredman Drive]: 98% complete


East bound (Section outside Old Mutual to be excluded) and 97% complete


West bound (Section outside Gautrain Hotel to be excluded)


- Storm water pipes: Excavation: 100% complete (East bound and West bound)
- Storm water pipes: Laying of pipes: 100% complete (East bound and West bound)
- Stormwater pipes: Backfill: 100% complete (East bound and West bound)
- Paving of medians: 100% complete
- Installation of sleeves and manholes: 100% complete East bound
(excluding section outside Old Village walk) and 100% complete
West bound (excluding section outside Gautrain Hotel)
- New pedestrian sidewalk: 100% complete
East bound (excluding section outside Old Village walk) and 100% complete
West bound (excluding section outside Old Village walk)
- BRT lane strengthening: 100% complete (excluding section outside Old Village walk)
- Base repairs: 100% complete
- New asphalt overlay: 95% complete
- Road marking: 30% complete
- Street lights: 100% complete


 


Phase 2: Maude Street [between West Street and Rivonia Road]: 99% complete


East bound and 98% complete West bound


- Storm water pipes: Excavation: 100% complete (East bound and West bound)
- Laying of pipes: 100% complete (East bound and West bound)
- Backfill: 100% complete (East bound and West bound)
- Installation of sleeves: 100% complete: Leonardo excluded (East bound and West bound)
- Expose existing services: 100% complete (East bound and West bound)
- Roadbed preparation: 100% complete Leonardo excluded (East bound) and (West bound)
- Layerworks: 100% complete Leonardo excluded (East bound) and (West bound)
- New paving Pedestrian side walk: 100% complete: Leonardo excluded (East bound) and 100% (West bound)
- New paving cycle lane: 100% complete: (West bound) and 100% complete East bound Leonardo excluded
- New paving vehicular lanes: 98% complete: (West bound) and 98% complete East bound Leonardo excluded
- Rumble blocks for cycle lanes: 100% complete (excluding Old Village walk)
- Painting of cycle lanes: 100% complete
- New dust bins: 100% complete
- Road marking: 0% complete (East bound and West bound)
- Road signage for metered taxis: 100% complete
- Egoli gas: 0% complete


Phase 2: Maude Street [between West Street and 5th Street]: 30% complete


- Setting out: 100% complete
- Exposing existing services: 50% complete
- Relocation of existing services: 50% complete
- New Storm water pipes: 40% complete
- New Sleeves: 50% complete
- New Pedestrian side walk: 35% complete
- Layerworks for road: 20% complete
- Landscaping: 0% complete
- Removal of median street lights: 70% complete
- New median street lights: 0% complete
- Re-alignment of median: 0% complete
- New paving of road: 0% complete


Phase 2: Fredman Drive [between Rivonia Road and 5th Street]: 99% complete


(West bound) & 99% complete (East bound)


- Storm water pipes: Excavation: 100% complete (East bound and West bound)
- Laying of pipes: 100% complete (East bound and West bound)
- Backfill: 100% complete (East bound and West bound)
- New Kerb inlets: 100% complete (West bound) and 100% (East bound)
- Installation of sleeves: 100% complete (West bound and East bound)
- Expose existing services: 100% complete (West bound and East bound)
- Lane widening by narrowing of median: 100%
- Paving of median: 100%
- New sleeves in median: 100%
- Base repairs: 100% complete (West bound)
- Base repairs: 100% complete (East bound)
- Crack sealing: 100% complete (East bound)
- BRT lane strengthening: 100% complete (West bound)
- Asphalt overlay: 100% complete (West bound) and 60% complete (East bound)
- New Pedestrian side walk: 100% complete (West bound) and 100% (East bound)
- Road marking: 70% complete
- New BRT station: 100% complete
- Street lights: 100% complete


 


Phase 2: 5th Street [between Fredman Drive and Rivonia Road]: 70% complete


(East bound) section outside Da Vinci excluded and 95% complete


(West bound) section outside WBHO excluded


- Installation of sleeves: 70% complete (East bound) and 100% complete (West bound)
- New Pedestrian side walk: 70% complete (East bound) and 100% complete (West bound)
- Retro-fitting of median: 100%
- Landscaping of median: 95% complete
- Raised driveways: 100% complete (West bound)
- Base repairs: 100% complete
- Asphalt overlay: 90% (East bound)
- Road marking: 0% (East bound)
- Street lights: 100% complete


Trunk route: Katherine Street [between West Street and 5th Street]: 100% complete


- BRT lane strengthening: 100% complete
- Paving of side walk East bound: 100% complete
- New kerb line median: 100% complete
- Paving of median: 100% complete
- Base repairs: 100% complete
- AP-1 Asphalt paving: 100%
- Road marking: 100% complete
- Street lighting: 100% complete
- Sleeves for street lighting: 100% complete


Trunk route: 5th Street [between Rivonia Road and Katherine Street]: 100% complete


- BRT lane strengthening: 100% complete
- Road widening: 100% complete
- Lowering existing services: 100% complete
- Paving of median: 100% complete
- Base repairs to South bound carriageway: 100% complete
- AP-1 Asphalt paving: 100%
- Road marking: 100% complete
- Street lighting: 100% complete
- Sleeves for street lighting: 100% complete


Trunk route: West Street [between Rivonia Road and Katherine Street]: 100% complete


- BRT lane strengthening: 100% complete
- AP-1 Asphalt paving: 100%
- Sleeve crossing: 100% complete
- Manhole for sleeves: 100% complete
- Reinstating Kerb inlet: 100%
- Base repairs: 100% complete
- Road marking: 100% complete
- Street Lighting: 100% complete
- Sleeves for street lighting: 100% complete


Issues during the week:


- Tim Dollar wants difference in plant rates paid to SMMEs: SMMEs want to claim the difference in plant rates from the JDA.


- Resolution: Total amount to be quantified and submitted to JDA for approval.


- Status: Pending