Rea Vaya phase 1C Sandton loop weekly report

 

Rea Vaya phase 1C Sandton loop weekly report for week ending 07 April 2017.

Phase 2: West Street South bound [between Maude Street and Rivonia Road]: 95% complete

- Storm water pipes: Excavation: 100% complete

- Laying of pipes: 100% complete

- Backfill: 100% complete

- New Kerb inlets: 100% complete

-New storm water manholes: 100% complete

- Installation of sleeves & manholes: 100% complete

- Road Widening: 100% complete

- Pedestrian side walk: 100% complete – Section outside Old Mutual to be excluded

- Base repairs: 100% complete

- Asphalt overlay: 100% complete

- Ramp outside Gautrain station: 100% complete

- Extra work Gautrain station: 0% (moving of steel hand railings, new hand railings on steps, wheel chair access ramp)

- Road signage for back-to-back kerbs of cycle lanes: 0% complete

- Bull nose for back-to-back kerbs of cycle lanes: 100% complete

- Bell mouths: 0% complete

- Road marking: 100% complete

- Planting of trees: 100% complete [West Street North bound outside Gautrain station]

- Street lights: 100% complete

- Egoli gas pipeline: 0% complete

Phase 2: West Street North bound outside Garden Court [between Maude Street and Alice lane]: 85% complete

- Expose existing services: 100% complete

- Excavation to sidewalk level: 100% complete

-Roadbed preparation: 100%

- Layer works to extend pedestrian side walk: 100% complete

- New paving to extend sidewalk to retaining wall: 100% complete

- New retaining wall: 100% complete

- New benches: 100% complete

- Hedge: 100% complete

- Bell mouths: 0% complete

-Re-location of palisade fence: 100% complete

Phase 2: Re-alignment of West Street North bound [between Fredman Drive and Grayston Drive]: 90% complete

- New kerbline of median: 100% complete

- Roadbed for median: 100% complete

- Layerworks for median: 100% complete

- Paving of median: 100% complete

- Asphalt for median: 100% complete

- Removal of median street lights: 100% complete

- Landscaping of median: 80% complete

- Bell mouths: 0% complete

- New kerbline for pedestrian sidewalk on West Street South bound: 100% complete

- Roadbed for pedestrian sidewalk on West Street South bound: 100% complete

- Layerworks for pedestrian sidewalk on West Street South bound: 100% complete

- Paving of pedestrian sidewalk on West Street South bound: 100% complete

Phase 2: Rivonia Road [between West Street and Fredman Drive]: 98% complete

East bound (Section outside Old Mutual to be excluded) and 97% complete

West bound (Section outside Gautrain Hotel to be excluded)

- Storm water pipes: Excavation: 100% complete (East bound and West bound)

- Storm water pipes: Laying of pipes: 100% complete (East bound and West bound)

- Stormwater pipes: Backfill: 100% complete (East bound and West bound)

- Paving of medians: 100% complete

- Installation of sleeves and manholes: 100% complete East bound (excluding section outside Old Village walk) and 100% complete West bound (excluding section outside Gautrain Hotel)

- New pedestrian sidewalk: 100% complete East bound (excluding section outside Old Village walk) and 100% complete West bound (excluding section outside Old Village walk)

- BRT lane strengthening: 100% complete (excluding section outside Old Village walk)

- Base repairs: 100% complete

- New asphalt overlay: 100% complete

- Road marking: 30% complete

- Bell mouths: 0% complete

- Street lights: 100% complete

Phase 2: Maude Street [between West Street and Rivonia Road]: 99% complete East bound and 98% complete West bound

- Storm water pipes: Excavation: 100% complete (East bound and West bound)

- Laying of pipes: 100% complete (East bound and West bound)

- Backfill: 100% complete (East bound and West bound)

- Installation of sleeves: 100% complete: Leonardo excluded (East bound and West bound)

- Expose existing services: 100% complete (East bound and West bound)

- Roadbed preparation: 100% complete Leonardo excluded (East bound) and (West bound)

- Layerworks: 100% complete Leonardo excluded (East bound) and (West bound)

- New paving Pedestrian side walk: 100% complete: Leonardo excluded (East bound) and 100% (West bound)

- New paving cycle lane: 100% complete: (West bound) and 100% complete East bound Leonardo excluded

- New paving vehicular lanes: 100% complete: (West bound) and 100% complete East bound Leonardo excluded

- Bell mouths: 0% complete

- Rumble blocks for cycle lanes: 100% complete (excluding Old Village walk)

- Painting of cycle lanes: 100% complete

- New dust bins: 100% complete

- Road marking: 100% complete (East bound and West bound)

- Road signage for metered taxis: 100% complete

- Egoli gas: 0% complete

Phase 2: Maude Street [between West Street and 5th Street]: 45% complete

- Setting out: 100% complete

- Exposing existing services: 50% complete

- Relocation of existing services: 50% complete

- New Storm water pipes: 50% complete

- New Kerb inlets: 20% complete

- New Sleeves: 50% complete

- Layerworks for new pedestrian side walk: 50% complete

- New Pedestrian side walk: 30% complete

- Layerworks for road: 50% complete

- Paving of median: 0% complete

- Bell mouths: 0% complete

- Removal of median street lights: 100% complete

- New median street lights: 0% complete

- Re-alignment of median: 0% complete

- New paving of road: 0% complete

Phase 2: Fredman Drive [between Rivonia Road and 5th Street]: 99% complete (West bound) & 99% complete (East bound)

- Storm water pipes: Excavation: 100% complete (East bound and West bound)

- Laying of pipes: 100% complete (East bound and West bound)

- Backfill: 100% complete (East bound and West bound)

- New Kerb inlets: 100% complete (West bound) and 100% (East bound)

- Installation of sleeves: 100% complete (West bound and East bound)

- Expose existing services: 100% complete (West bound and East bound)

- Lane widening by narrowing of median: 100%

- Paving of median: 100%

- New sleeves in median: 100%

- Base repairs: 100% complete (West bound)

- Base repairs: 100% complete (East bound)

- Crack sealing: 100% complete (East bound)

- BRT lane strengthening: 100% complete (West bound)

- Asphalt overlay: 100% complete (West bound) and 100% complete (East bound)

- Bell mouths: 0% complete

- New Pedestrian side walk: 100% complete (West bound) and 100% (East bound)

- Road marking: 70% complete

- New BRT station: 100% complete

- Street lights: 100% complete

Phase 2: 5th Street [between Fredman Drive and Rivonia Road]: 70% complete

(East bound) section outside Da Vinci excluded and 95% complete

(West bound) section outside WBHO excluded

- Installation of sleeves: 70% complete (East bound) and 100% complete (West bound)

- New Pedestrian side walk: 70% complete (East bound) and 100% complete (West bound)

- Retro-fitting of median: 100%

- Landscaping of median: 100% complete

- Raised driveways: 100% complete (West bound)

- Base repairs: 100% complete

- Asphalt overlay: 100% (East bound)

- Road marking: 0% (East bound)

- Bell mouths: 0% complete

- Street lights: 100% complete

Trunk route: Katherine Street [between West Street and 5th Street]: 100% complete

- BRT lane strengthening: 100% complete

- Paving of side walk East bound: 100% complete

- New kerb line median: 100% complete

- Paving of median: 100% complete

- Base repairs: 100% complete

- AP-1 Asphalt paving: 100%

- Road marking: 100% complete

- Street lighting: 100% complete

- Sleeves for street lighting: 100% complete

Trunk route: 5th Street [between Rivonia Road and Katherine Street]: 100% complete

- BRT lane strengthening: 100% complete

- Road widening: 100% complete

- Lowering existing services: 100% complete

- Paving of median: 100% complete

- Base repairs to South bound carriageway: 100% complete

- AP-1 Asphalt paving: 100%

- Road marking: 100% complete

- Street lighting: 100% complete

- Sleeves for street lighting: 100% complete

Trunk route: West Street [between Rivonia Road and Katherine Street]: 100% complete

- BRT lane strengthening: 100% complete

- AP-1 Asphalt paving: 100%

- Sleeve crossing: 100% complete

- Manhole for sleeves: 100% complete

- Reinstating Kerb inlet: 100%

- Base repairs: 100% complete

- Road marking: 100% complete

- Street Lighting: 100% complete

- Sleeves for street lighting: 100% complete

 Issues during the week:

- None

 Report prepared by: Isaac Ojungu

Pr.Eng Msc Eng (Transport)

Resident Engineer

BERGSTAN SA